![]() (Click to enlarge) |
Land
Assembly/Alienation Thus one may find that in one precinct the development process is virtually complete in that the following activities have been finalised: land claims, planning, installation of infrastructure, survey, registration of land consolidation and the opening of a township register, whereas in another precinct only one or two of these activities have received attention. Consolidations It was left to the CMDA as agent of the Provincial Housing Development Board to complete the consolidation process and this was achieved by registering three further consolidations of 22 properties, 204 properties and 181 properties during June, August and November 1997 respectively. | |
|
It was extremely important that these consolidations were registered as it facilitated the registration of new layout plans and the opening of the relevant township registers. Unless this process had been completed, transfers of the new erven to the prospective purchasers could not be effected. Township Establishment Sales Allocations Land Claims The Agreement is the first of its kind in the country and has allowed the Cato Manor project to proceed whilst claims are being resolved. Restitution options for claimants have been established and include financial compensation, alternative land in Cato Manor and, where feasible, restoration of the original land holding. A complex process to settle the claims was established but can be summarised very simply as follows:
The majority of the claimants, the CMDA, the RLCC and the DLA have been working hard an continuously to make the settlement agreement work. Although slower than hoped, substantial progress has been achieved during 1998 as reflected by the statistics in the table below: During 1998 a group of claimants, subsequent to the signing of the Settlement Agreement, elected to bring an application before the Land Claims Court for an interdict to stop development on certain areas of the project. The application was dismissed with costs by the Court. Land Claims A series of challenges around land issues were successfully dealt with between 1993 and 1997 including substantial achievements in combating land invasions and resolving matters associated with the restoration of land rights. In 1994 a Commission on Restitution of Land Rights and a Land Claims Court were established to investigate and address the claims of people dispossessed of land under apartheid. A total of 5 722 land claims were received by the Commission in respect of properties in Cato Manor. Due to the time that would have been needed to validate and settle this volume of claims, a strategy aimed at addressing legitimate claims, whilst allowing the development to proceed, had to be developed. Accordingly, the CMDA placed an application before the Land Claims Court in terms of Section 34 of the Restitution of Land Rights Act No. 22 of 1994, requesting, in the interests of the holistic and sustainable development of Cato Manor, that land not be restored to individual claimants and that other forms of redress such as alternative land or financial compensation be used. Over 400 former residents opposed the Application. Following a protracted court case and months of negotiations, the historic Land Claims Settlement Agreement, the first of its kind in South Africa, was signed in May 1997, enabling the development to proceed whilst claims were being resolved. Restitution options for claimants included financial compensation, alternative land in Cato Manor and, where feasible, restoration of the original land holding. The position at the end of 2002 in respect of Cato Manor land claims which have been processed in terms of the Section 34 Settlement Agreement is as follows: • 302 claims were settled on the basis
of ‘financial compensation’. Relocattions The CMDA has already successfully created housing opportunities for more than 200 families who have had to move out of the way of bulk services implementation. A brief description of the key steps in the relocation process is as follows:
Some of the larger projects where relocations have successfully been implemented include the following:
|
||
|
what's new |overview
| key dimensions | map | management
| eu assistance |reports | history |
press | contact | links
|