Bellair Road Upgrade Project
This project extends from Francois Road to Jan Smuts
Highway. It is funded jointly by the RDP and the Metro
Council, and has a total value of R26.4 million. The
work is being done in phases.
|

Phase two of the Dunbar
Collector Road is already underway.
|
Phase 1:
Concor Road has a contract to upgrade Bellair Road
from Francois Road to the Mayville sub station. The
extension of the road was completed in December 1999.
Phase 2A:
The contract to extend Bellair Road from the Mayville
sub station to Wiggins Road was awarded to Asphalt
Construction. Work is scheduled for completion in
March this year.
Phase 2B:
The design for the extension of Bellair Road from
Wiggins Road to Jan Smuts Highway is complete, and
construction will begin this year.
|
 |
COMMUNITY
FACILITIES
|
|
Multi-Purpose Centre, Cato Crest:
The primary school is in operation and renovation
work is continuing and will be completed this month.
Part of the secondary school has also been completed.
|

Work at the Cato Crest
Multi Purpose Centre funded by the European Union is
nearing completion as evidenced by the community hall
shown in the picture. Completion date is set for April
this year, weather permitting.
|
Seven classrooms and the administration block are
already being used for grade eight pupils.
The library and the community hall are scheduled
for completion in April 2000. The rest of the secondary
school and the sports field are scheduled for completion
this month.
|
Pre-schools:
A contract has been awarded for two RDP funded pre-schools
to be built in Nsimbini and New Dunbar. While construction
on the Nsimbini site started in December last year
work on the New Dunbar pre-school project is delayed
by the slow progress of relocations.
|
Primary School:
Work on the primary school in Molver Road, Cato Crest
is well underway and is due for final completion in
November 2000.
|

Stakeholders in the construction
of a primary school along Molver Road in Cato Crest
gather to inspect the plans during a site hand over
meeting held in the area recently.
|
|
Secondary School:
The secondary school that is being built along Dennis
Shepstone Road in Chesterville Extension will be completed
in October 2000.
|
Library:
The RDP funded public library under construction in
Booth Road should be completed at the end of April.
|

Work on the RDP funded
library at Chesterville Extension is going according
to plan. The library will be open to the public this
year.
|
|
Bellair Urban Market & Urban Park:
Construction of the urban park is scheduled for completion
in March and the market in April 2000.
|

The informal market under
construction in Bellair Road will be up and running
at the end of April. Construction of the market is funded
by the RDP.
|
|
Bellair Shopping Centre:
The new shopping centre is well underway, although
delays were experienced due to heavy rainfall. Completion
is now scheduled for the end of April.
|

The Shopping Centre under
construction on Bellair Road.
|
|
Chesterville Extension Community Hall:
Construction is due to commence in March.
|
more stories on next page....CLICK
HERE